Buyer’s guide
Preparing your shop for a CNC router
Delivery day is a terrible time to discover the doorway is four inches too narrow or the panel can’t feed the spindle. Here’s everything to have ready before the truck rolls: space, floor, power, air, dust, rigging, and people.
The preparation timeline
1
When you order
Get the machine's site prep sheet: weight, dimensions, electrical spec, air spec. Book your electrician and schedule the receiving rigger.
2
Weeks before
Run power and air to the machine's spot, pour or verify the floor, install dust ducting, and clear the path from the door to the footprint.
3
Delivery day
Dock or forklift ready, path clear, decision-maker on site. The rigger sets the machine on its marks; nothing gets hooked up in a hurry.
4
First weeks
Leveling, commissioning, and training. Operators learn the machine on real parts and the maintenance schedule starts on day one.
Space and layout: think in sheets, not footprints
The machine’s footprint is the smallest number in the room. A nested-based router eats full sheets on one end and gives up finished parts on the other, so both ends need staging space: a cart or lift of raw material within reach, and somewhere for parts to land. Add walkway clearance on the sides, room for the electrical cabinet door to swing fully open, and access to reach the far side of the table for cleaning and maintenance.
Before you commit to a spot, sketch the material flow through the whole shop: where sheets come off the truck, where they’re stored, how they get to the machine, and where parts go next. Machines placed for material flow earn more than machines placed where there happened to be a gap. And check the ceiling: dust drops, tool-length sensors, and an open gantry hood all want headroom.
The floor: level, sound, and strong along the whole path
Most CNC routers are happy on a sound, level concrete slab, with their leveling feet taking out minor variation. What matters is that the slab is in good condition and reasonably level across the machine’s footprint; a common rule of thumb is within about a half inch across the machine, then fine-leveled at the feet. Cracked, spalled, or badly out-of-level concrete makes precision machinery’s life hard and yours harder.
Two details people miss: the floor has to carry the machine along the delivery path, not just at the final position, so know your slab before a forklift carries five tons across it. And if the machine gets anchored, that’s a spec from the manufacturer’s site prep sheet, not a judgment call.
Electrical: the spec sheet, an electrician, and no shortcuts
Industrial CNC routers generally run on three-phase power at 208, 230, or 460 volts, on a dedicated circuit with a disconnect and a solid earth ground. The ground isn’t bureaucracy: CNC controls are sensitive electronics, and poor grounding shows up as mystery faults, interference, and dead boards. Mid-size machines commonly draw on the order of 30 to 40 amps, but spindle size, vacuum pumps, and accessories swing that number widely, so hand the machine’s electrical spec to a licensed electrician early and let them size wire and breaker to code. Codes generally require sizing the service as if everything in the building runs at once, so list every machine, not just the new one.
No three-phase in the building? You have two options: ask the utility what it costs to bring it in, or install a phase converter. For CNC work the proven answer is a rotary phase converter sized at roughly twice the horsepower of the largest motor it starts; static converters aren’t suited to production CNC loads, and VFD-based conversion fits single-motor situations only. Unstable or undersized power shows up later as inconsistent spindle speeds, servo faults, and interrupted programs, so this is the corner not to cut.
Compressed air: it's the quality, not the quantity
The router’s appetite for air is modest: tool changers, pod clamping, and pop-up pins typically want clean, dry air in the 90 to 120 PSI range, and if your shop line runs higher than that, a regulator at the machine brings it down. The volume is rarely the problem. The moisture is.
Water in the air line is the quiet killer of tool changers and pneumatic components. A compressor that short-cycles runs hot and pushes moisture-laden air straight down the line, and desiccant cartridges give up quickly in a working shop. The reliable setup is a properly sized compressor that isn’t constantly cycling, a refrigerated air dryer sized to the compressor’s output, and drops plumbed so condensation drains away from the machine. Shops routinely spend six figures on the machine and fifty dollars on air treatment; don’t be that story.
Dust collection: size it for the machine, not the broom
A CNC router is one of the hungriest dust producers in the shop, typically wanting around 800 CFM or more at the hood with enough velocity in the duct to keep chips moving. That’s a real duct run and a real collector, not a shop vac. Undersized dust collection doesn’t just make a mess: it packs the cut with chips that get re-cut, which burns tools and finishes.
Plan the duct route to the machine’s spot before delivery, keep flex hose to the last few feet, and put a blast gate on the branch. Our dust collection CFM calculator totals the airflow for whatever combination of machines runs at once and suggests a main duct size. Commercial shops also carry combustible dust obligations (NFPA standards and local fire code), which is one of several reasons production systems are worth engineering properly.
Vacuum hold-down: the other big motor
On a nested router, the vacuum pump that holds sheets to the spoilboard is often the largest electrical load after the spindle, and sometimes before it. It needs its own line on the electrical plan, a home where its heat and noise won’t bother anyone, and plumbing to the table. If the machine you’re buying includes a pump, its draw is on the same spec sheet; make sure your electrician sees it.
Budget one more consumable while you’re at it: spoilboards. The MDF sacrificial layer gets surfaced regularly to stay flat and porous, so a stack of spoilboard blanks and the surfacing bit to dress them belong on the day-one supplies list.
Environment: electronics and wood agree on this one
CNC controls want what wood wants: a clean, dry space without temperature extremes. Big swings in temperature and humidity move both the machine’s electronics and your material; damp environments corrode components and rust cast iron and rails. Keep the machine away from wash bays, open overhead doors that let weather blow across it, and direct radiant heat.
If the shop gets cold overnight in a Michigan winter, plan for the machine to warm up before it cuts precision work, and keep the control cabinet’s cooling vents clear of dust buildup as part of the maintenance routine.
Network and software: the machine is a computer now
Programs have to get to the machine, and support has to get to the control. Run a wired network drop to the machine’s location: file transfer over a cable beats USB sticks, and remote diagnostics, when a technician can look at the control from afar, turns some service calls into ten-minute fixes.
Decide where the CAD/CAM work happens, too. Most shops program at a workstation near, but not at, the machine, and walk the file over the network. Get software licenses, post processors, and the programming seat sorted before delivery so training time goes to cutting parts, not installing software.
Delivery and rigging: the trucker hauls, the rigger sets
The single most useful thing to know about delivery day: the freight carrier and the rigger are two different jobs. The truck brings the machine; a rigger, with the right forklift and the experience to use it, unloads, moves, and sets it on its marks. Most delivery-day disasters come from assuming one includes the other. Schedule the receiving rigger before the machine ships.
Give the rigger the machine’s exact weight and crated dimensions from the spec sheet. Industrial routers commonly weigh 5,500 to over 11,000 pounds, which dictates forklift capacity and whether your dock, door, and path can handle the move. Measure door widths and heights against the crate, walk the path for obstructions, and have someone with decision-making authority on site during the window. If any of that sounds like a lot, it’s the part we routinely coordinate for our customers; ask us early and delivery day gets boring, which is the goal.
People and the first weeks: the machine is the easy part
Decide who runs the machine before it arrives, and protect their training time. Commissioning and initial training take days, and an operator who learns on real production parts, with the trainer standing there, gets to profitable throughput weeks faster than one who inherits a manual. If you’re moving an operator from manual machines, feeds-and-speeds discipline is the biggest new skill; our chip load calculator is the cheat sheet.
Start the maintenance schedule the day the machine starts: lubrication, rail and rack cleaning, filter checks, spoilboard surfacing. Machines that get a schedule from day one are the ones still cutting straight in year fifteen. And if you’re still weighing whether the machine pays, run the machine ROI calculator with honest numbers first.
The site prep checklist
Print it, stick it to the wall, and delivery day gets boring.
Paperwork & planning
- Site prep sheet from the machine builder in hand
- Machine weight and crated dimensions confirmed
- Electrician has the electrical spec
- Receiving rigger scheduled before the machine ships
- Insurance certificates squared away
The building
- Door and ceiling clearances measured against the crate
- Clear, level path from door to footprint
- Floor verified level and sound where the machine lands
- Machine footprint marked out with working clearances
- Material staging space at the load and offload ends
Utilities
- Dedicated circuit, disconnect, and grounding installed
- Three-phase power or converter/transformer in place
- Compressed air at the spec pressure, with a dryer
- Dust collection sized, ducted, and gated
- Network drop at the machine and at the CAD/CAM station
People
- Operator(s) chosen and training scheduled
- Forklift or dock arrangements confirmed for delivery day
- Decision-maker on site for the delivery window
- Maintenance schedule ready to start day one
Site preparation FAQs
Do I need three-phase power for a CNC router?
Industrial machines almost always want it: three-phase delivers smoother power, and spindles, vacuum pumps, and servo systems run better and last longer on it. Common supply voltages are 208, 230, or 460 volts three-phase. Entry-level machines may run on single-phase 220V. Your machine's spec sheet states exactly what it needs; get it to your electrician early.
What if my building only has single-phase power?
You have two paths: ask the utility what bringing three-phase to the building costs, or install a phase converter. For CNC equipment, a rotary phase converter is the proven choice, sized at roughly twice the horsepower of the largest motor it will start. Static converters aren't suitable for production CNC work, and VFD-based conversion only fits single-motor situations.
How much compressed air does a CNC router need?
Less volume than people expect, but the quality matters enormously. Tool changers, pod clamping, and pop-up pins typically want clean, dry air at roughly 90 to 120 PSI; if your line runs higher, add a regulator. The killer is moisture: water in the line ruins tool changers and pneumatics, so budget for a refrigerated air dryer sized to your compressor, not just the compressor itself.
How much does a CNC router weigh?
Entry-level 4x8 machines start around 2,000 pounds, and industrial 5x10 routers commonly run 5,500 to over 11,000 pounds. That number drives everything about delivery: the truck, the forklift capacity, the path into the building, and whether the floor along that path can take it. Get the exact figure from the spec sheet before anything ships.
Who unloads and places the machine?
Not the freight carrier: the trucker hauls the machine, and a rigger lifts, positions, and sets it. They're separate services, and most delivery-day problems come from assuming one includes the other. Schedule the receiving rigger before the machine ships, confirm forklift capacity against the machine's weight, and have someone with authority on site during the unload.
Do I need a special foundation?
Usually not: a sound, level concrete slab handles most CNC routers, and leveling feet take out minor variation. What you're checking is that the slab is in good condition, roughly level across the footprint, and strong enough along the delivery path as well as at the final position. Very large or high-precision machines may have specific slab requirements, which the site prep sheet will state.
How much space should I leave around the machine?
More than the footprint suggests. You load full sheets on one end and pull parts off the other, so both ends need room for material handling, plus walkway and maintenance access on the sides and clearance for the electrical cabinet to swing open. Sketch the material flow, from storage to machine to assembly, before you commit to a spot.
How long does installation and training take?
Plan on days, not hours: setting and leveling the machine, hooking up power, air, and dust, commissioning, and initial operator training. The schedule depends on the machine and how ready the site is, which is exactly why the preparation in this guide pays for itself. We walk through all of it with you when we quote the machine.
Or let us walk the floor with you.
Every machine we quote comes with this conversation: site requirements, delivery coordination, installation, and training, planned before anything ships. Sixty years of deliveries means we’ve seen the doorway that’s four inches too narrow, and we measure it first. Our service team stays with the machine long after delivery day.